The hotel is located in Kadaster Palace, opposite the city center station. The hotel has got 100 rooms and a ground floor with a basement dedicated to artwork showing and carrying out of cultural and social events. The job is part of a general upgrading project for the Kadaster building.
All rooms are acoustically isolated from impact sound by the application of GREI installed in a dry system by using the Isolgomma product with Fermacell panels.

Problem.

Often, dry solutions are used in order to reduce construction time. Obviously from the acoustic point of view it is important to collaborate with companies that have certified products for dry systems.

Suggested solution.

Taking advantage of the specific activity carried out by Isolgomma to study the acoustic behaviour of its materials in combination with dry solutions, it was possible to provide the project manager with all the support needed to dimension the various solutions and obtain very high levels of acoustic comfort.

Result.

Project realization times respected, achieved the insulation parameters defined by the customer.